Regional grid operator PJM Interconnection has selected a major electric transmission project to meet a critical ...
HARRISBURG --- More than 50 people have written letters protesting the construction of a Transource high voltage transmission line through Franklin County. Tuesday is the final day to submit letters ...
The proposed Transource project has prompted extensive discussion about the adverse impact high voltage power lines may have on Franklin County tourism, economic development, land use, the environment ...
The company hired to build a $320 million high-voltage overhead power line took 36 southern York County landowners to court Wednesday, April 25, in a civil lawsuit. Transource Energy said the project, ...
Northern Harford County community leaders battling Transource Energy’s $320 million project to build new power lines through their properties urged local legislators last week to pursue bills to ...
Here’s a sweet business deal for you: Imagine you were working on a project to build a new widget factory in York County. That kind of project comes with inherent risks. Maybe you’ll run into zoning ...
A controversial power line project should be rejected because it serves little purpose and would have “detrimental” economic and environmental effects for nearby land owners, a Public Utility ...
The proposal includes more than 300 miles of new 765-kilovolt (kV) transmission lines and upgrades to multiple substations.
Regional grid operator PJM Interconnection has selected a major electric transmission project to meet a critical ...