Open links in new tab
  1. Need comparison between CDEGS and WinIGS | Eng-Tips

    Jan 28, 2010 · Hi Fellows, We are currently using CDEGS software package for grounding system design an analysis. From one of IEEE surveys I found that WinIGS is also very popular these days …

  2. CDEGs MALT and MALZ program | Eng-Tips

    Oct 26, 2012 · We currently have CDEGS Multiground with MALT program, is MALZ program required for Substation Grounding Analysis?

  3. CDEGS | Eng-Tips

    Oct 9, 2016 · CDEGS said: The concrete foundations reinforcement bars are generally connected to the grounding grid and may improve the grounding performance of the grid. The concrete itself, being a …

  4. Wind/Solar Collection System, CDEGS FCDIST Calculation

    Aug 17, 2015 · Assume a substation with one transmission source and one collector feeder. The transmission source has shield wires which are connected on both ends, and the collector system is …

  5. Grid modeling with CDEGS | Eng-Tips

    Aug 27, 2011 · I am using Malz in Cdegs to analyse and model the grid of a substation.Does any one know how I can find the induced voltage on a metal pipe 50 meters below my grid and ensure that …

  6. CDEGS error | Eng-Tips

    Apr 13, 2021 · Hi everyone, I am learning CDEGS recently, I found out "there are defects in the grounding grid during simulation, Use the diagnostic tool for more information. Does any body …

  7. CDEGS - Current Flowing - Plotting | Eng-Tips

    Jul 21, 2023 · How could I plot current flowing in a conductor, with x-axis being the distance from the origin of the conductor and the y-axis being the value of current flowing at this segment ? I am using …

  8. CDEGS HIFREQ Cable Design Voltage Potential Calculations

    Jul 20, 2023 · Hi, I am a new CDEGS user and I am trying to design a 3-core cable. I am using define -> cable type to enter cable properties in SESCAD. Although induced sheath currents are calculated …

  9. grounding grid observation profile in CDEGS | Eng-Tips

    Jan 7, 2023 · Hello, IEEE std 80-2013 mentioned grounding grid is normally set 3-4 feet extension out of the station fence boundary. And in CDEGS, the observation profile is set at another 3 feet extension …

  10. CDEGS Potential Plot values (Spot levels x 1.E+3) | Eng-Tips

    Apr 13, 2023 · Hello, I'm trying to understand the reason why the maximum and the threshold values in the plot snip attached show as 1.E+3 instead of the actual values...